2-8 BA 1404 en – Edition 2.7 * * 1404b210.fm
Safety instructions
2.9 Trailers and attachments
Fit the attachments with the specially required devices only!
Before uncoupling or coupling hydraulic lines (hydraulic quick couplers)
Stop the engine
Relieve hydraulic oil pressure in the hydraulic system; do this by moving the
operating levers of the hydraulic control units to and fro several times
Coupling attachments requires special care!
Secure the attachments against unintentional movement!
Operate the machine only if all protective facilities have been installed and are
functional, and if all brake, light and hydraulic connections have been connected!
If optional equipment is installed, all lighting equipment, indicator lights, etc. that are
required in addition must be installed and functional
Install the attachments only if the engine and the drive have been switched off
Especially when performing machine travel and operation with machines equipped with
a quickhitch for the attachments, ensure that the attachment is securely locked in the
quickhitch. The lock pin must be visible on either side of the bores on the attachment.
Check again before starting work.
Raise the control lever base before installing attachments on the stick.
Be careful when coupling attachments to the machine: injury hazard due to crushing
and shearing. Ensure that nobody is between the machine and the attachment!
2.10 Transportation
The machine must be towed, loaded and transported only in accordance with the
Operator’s Manual!
For towing the machine observe the prescribed transport position, permissible speed
and itinerary.
Use only suitable means of transport of appropriate capacity/payload!
Safely secure the machine on means of transport! Use suitable tie-down points and
load-securing devices.
The recommissioning procedure must be strictly in accordance with the Operator’s
Manual!
Tighten the cab fastening screws to the specific torque before raising the machine.
2.11 Working in the area of underground electric lines
Before starting any work, the machine operator must ensure that there are no lines on
the job site.
If you are not sure, contact the person in charge at the network operator.
If there are lines, take the following safety measures:
Mark the position and path of the lines unambiguously
Fasten, support or secure exposed lines
Safely fasten lines if vibration or shocks to these lines must be avoided

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson E09-01 and is the answer not in the manual?

Wacker Neuson E09-01 Specifications

General IconGeneral
BrandWacker Neuson
ModelE09-01
CategoryExcavators
LanguageEnglish

Related product manuals