EasyManuals Logo
Home>ABB>Industrial Equipment>ACS2000

ABB ACS2000 User Manual

ABB ACS2000
214 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #136 background imageLoading...
Page #136 background image
7-4 (6) 2UEA001270 Rev. F ACS2000 User manual
Chapter 7 - Commissioning
MV switchgear
Motor
Insulation tests
1 Type of MV switchgear selected and wired per ABB MV switchgear specification
2 MV switchgear ready to be tested with drive
3 MV switchgear protection relay settings tested
4
Safety devices (door locks, Kirk
®
key, grounding switch, etc.) tested and in operation
5 MCB IS EXCLUSIVELY CONTROLLED BY THE ABB DRIVE
1 Motor installed, aligned and alignment protocol available
2 Motor not coupled to driven load
3 Ground connection completed
4 Motor auxiliaries (bearing lubrication, heater cooling, etc.) ready
1 All power cables to input transformer, between input transformer and drive, and from
drive to motor are meggered, and measured values are within the required limits
2 Test report of the megger test available
Note: If the test is carried out by the commissioning engineer of the drive, an additional
day per drive motor combination needs to be reserved. The test must comply with the
specification.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB ACS2000 and is the answer not in the manual?

ABB ACS2000 Specifications

General IconGeneral
BrandABB
ModelACS2000
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals