7-4 (6) 2UEA001270 Rev. F ACS2000 User manual
Chapter 7 - Commissioning
MV switchgear
Motor
Insulation tests
1 Type of MV switchgear selected and wired per ABB MV switchgear specification
2 MV switchgear ready to be tested with drive
3 MV switchgear protection relay settings tested
4
Safety devices (door locks, Kirk
®
key, grounding switch, etc.) tested and in operation
5 MCB IS EXCLUSIVELY CONTROLLED BY THE ABB DRIVE
1 Motor installed, aligned and alignment protocol available
2 Motor not coupled to driven load
3 Ground connection completed
4 Motor auxiliaries (bearing lubrication, heater cooling, etc.) ready
1 All power cables to input transformer, between input transformer and drive, and from
drive to motor are meggered, and measured values are within the required limits
2 Test report of the megger test available
Note: If the test is carried out by the commissioning engineer of the drive, an additional
day per drive motor combination needs to be reserved. The test must comply with the
specification.