Chapter 4 Functional Checks 4 - 3
4-2-1-2 Power Up
1.) Connect the Power cable to an appropriate mains power outlet
2.) Press Front Panel ON/OFF
key once to Switch ON/OFF
When power is applied to the Scanner, Power is distributed to the Fan, Control panel, Monitor, Internal
and External I/O’s, Boards & Peripherals. Back End Processor starts and its software code is distributed
to initiate the scanner.
Power Up Display Comes Up. Refer figure 4-29.
4-2-1-3 Power Shutdown
1.) Switch OFF the ON/OFF
at the Front of the system.
2.) Disconnect the Mains Power Cable if needed.
Figure 4-27 Mains Circuit Breaker and Mains Power Cable
Figure 4-28 ON/OFF key on Front Panel
Mains Power
Cable Connector
Main Circuit Breaker