8-1
ET 200S Interface Module IM 151/CPU
A5E00058783-01
Getting Started
Introduction
This guide takes you through the 10 commissioning steps required to set up a
functioning application by running through a concrete example. In this way, you will
get to know the basic functions of your IM 151/CPU for the following:
Hardware and software
Stand-alone operation and as an intelligent DP slave
Prerequisites
You must be familiar with the fundamentals of electronic/electrical engineering and
have experience of working with computers and Microsoft Windows 95/98/NT.
!
Danger
The IM 151/CPU-ET 200S and the S7-300 are used in installations and systems that require
you to comply with specific rules and regulations that vary depending on the application.
Please note the relevant safety and accident-prevention regulations, such as IEC 204
(emergency stop systems).
Non-compliance with these regulations can result in serious injury and damage to both
machinery and equipment.
Chapter Overview
In
Section
Contents Page
8.1 Step 1: Installing the ET 200S/IM 151/CPU and S7-300 8-3
8.2 Step 2: Wiring the ET 200S/IM 151/CPU and S7-300 8-4
8.3 Step 3: Commissioning of the ET 200S/IM 151/CPU 8-5
8.4 Step 4: Configuring the IM 151/CPU for Stand-Alone Operation 8-6
8.5 Step 5: Programming the IM 151/CPU 8-8
8.6 Step 6: Test Run 8-9
8.7 Step 7: Upgrading the IM 151/CPU and Commissioning the S7-300 8-10
8.8 Step 8: Configuring the IM 151/CPU as a DP Slave and the S7-300
as a DP Master
8-11
8.9 Step 9: Programming the IM 151/CPU and the S7-300 8-14
8.10 Step 10: Commissioning and Test Run 8-16