Four-post rack—a freestanding open rack, either open or closed
•
The rack must have at least two mounting posts.
•
The distance between the mounting holes in the two posts must be 18.31 in. +/-.063
in., as specified in the EIA-310-D document.
•
A fully loaded rack with three CTP2056 systems must structurally support at least 100
lb (46 kg).
•
An optional mounting kit is available for midchassis mounting. Contact your Juniper
Networks sales representative for more information.
Related
Documentation
CTP2000 Rack Requirements on page 39•
• CTP2000 Space Requirements on page 40
• CTP2000 Rack Installation on page 40
CTP2000 Space Requirements
If you use an enclosed rack for the device, ensure that there is a minimum of 3 in. of
clearance between the inner side wall and the system. This clearance space ensures
adequate air flow.
Related
Documentation
CTP2000 Rack Requirements on page 39•
• CTP2000 Mechanical Requirements on page 39
• CTP2000 Rack Installation on page 40
CTP2000 Rack Installation
To confirm proper equipment rack installation, verify the following:
•
Racks are installed and electrically grounded according to manufacturer instructions.
•
Equipment racks are anchored to the floor and, when possible, anchored to the ceiling
as well.
•
Equipment rack installations comply with applicable local, state, and national codes.
Related
Documentation
CTP2000 Mechanical Requirements on page 39•
• CTP2000 Rack Requirements on page 39
• CTP2000 Space Requirements on page 40
• Special Guidelines for Installing CTP2056 Chassis in a Rack on page 84
CTP Cabling Recommendations
We suggest that you comply with the following recommendations:
Copyright © 2017, Juniper Networks, Inc.40
CTP2000 Hardware Documentation