Manitowoc Published 11-20-19, Control # 234-19 4-131
MLC300 OPERATOR MANUAL SETUP AND INSTALLATION
Prepare VPC Trolley for Shipping
NOTE Disregard this procedure if the VPC trolley is not
being removed for shipping.
See Figure 4-88
for the following procedure.
1. Install the hose storage bracket (10, View D) on the VPC
trolley.
2. Disconnect the dust caps from the couplers on the hose
storage bracket.
3. Attach a lifting sling from the fork of the forklift or from an
assist crane to the lifting link (14, View H) on the energy
chain (3).
4. Lift the energy chain off the energy chain support (4,
View H) and remove the energy chain support from the
working position (View E).
5. Install the energy chain support (4, View C) in the
shipping position on the VPC trolley (2).
6. While holding the energy chain with the lifting sling:
a. Remove the energy chain supports (12 and 13) from
storage in the job box.
b. Install the energy chain supports (12 and 13, View
B) in the shipping positions.
c. Lower the energy chain onto the supports as shown
in View B and disconnect the lifting sling.
d. Install pins (11, View B) in the holes in the energy
chain supports (12 and 13).
7. Connect the hydraulic hoses (9, View D) to the couplers
on the storage bracket (10).
8. Position the trailer (1, View A) in the assembly area.
9. Position the forks from a forklift under the trolley at the
locations shown in View A OR attach lifting slings from
an assist crane to the four lifting lugs (18, View A) on the
trolley frame.
10. Lift the VPC trolley onto the trailer and place it on
blocking to prevent damaging the parts under the trolley
frame.
11. Secure the VPC trolley to the trailer with tie-downs.
12. Remove the forklift of disconnect the lifting slings.
Figure 4-88 continued
View E
WORKING
View H
WORKING