Manitowoc Published 04-06-18, Control # 231-14 4-81
MLC650 VPC-MAXâ„¢ OPERATOR MANUAL SET-UP AND INSTALLATION
See Figure 4-68 for the following procedure.
6. Install the block-up limit components at the boom points.
7. If equipped with a jib, continue to raise the boom until the
jib point is at a convenient height to install the load block
or the hook-and-weight ball.
a. Signal the operator to STOP raising the boom if the
jib pendants get caught on the brackets, pins, or
timber guards. Correct the problem before
continuing.
b. Make sure the jib stop pins are properly installed.
8. Install the load block or hook-and-weight ball at the jib
point.
9. Install the block-up limit components at the jib point.
10. Continue to boom up until the boom is at an angle that
safely allows the load block(s) and hook-and-weight ball
to be lifted.
11. Once the boom is raised, perform the following checks:
a. Check all crane functions for proper operation.
b. Check all safety devices for proper operation (see
Section 3 of the MLC650 Operator Manual).
c. Make sure the boom stop is adjusted for the proper
maximum boom angle.
d. Make sure the RCL/RCI is properly calibrated.