Manitowoc Published 04-06-18, Control # 231-14 4-129
MLC650 VPC-MAXâ„¢ OPERATOR MANUAL SET-UP AND INSTALLATION
Moving Tray Pinions out of Mesh
See Figure 4-108 for the following procedure.
1. Using the assist crane, hoist just enough to remove the
slack from the pendants.
NOTE: Do not hoist the tray off the VPC-MAX beam. The
tray must still be supported by the rollers.
2. Using the remote control, move the tray back until the
pinions (1) are no longer in mesh with the rack teeth (2).
3. Using the assist crane, move the tray back an additional
50 mm (1.97 in) to make sure the pinions are clear of the
rack teeth.
FIGURE 4-108
Item Description
1 Pinion (qty 2)
2 Rack Teeth