Pass-thru Port Planning
Installation Planning 2-11
inch) square and 1.2 mm (0.048 inch) thick, cover the openings and can be drilled to
custom fit nozzles. Nozzles must be clear of robotic operations and cannot protrude
more than 2.54 cm (1 inch) into the library. Professional Services can assist with fire
suppression planning (contact your Oracle sales representative).
Figure 2–4 Fire Suppression Ceiling Access (viewed from the top of the library)
Figure Legend:
1. Datum (measurements are without covers or doors)
2. Nozzle cutout
Pass-thru Port Planning
Although the library complex can expand in either direction, adding a new library to
the left is non-disruptive. To expand the library complex in the other direction, you
must bring the library offline to re-configuration the system and re-IPL the library.
Figure 2–5 shows two examples of a three-library complex.
■ Example 1, on the left, shows the preferred non-disruptive method of adding
another library (C) to the left of the library complex.
■ Example 2, on the right, shows the disruptive method. Adding another library (C)
to the right of the library complex requires a reconfiguration of LSM numbering.