5 Mechanical Installation
Respect all local standards and requirements during mechanical installation.
5.1 Transport
All devices are installed inside the inverter before delivery. The inverter should be
transported as a whole. Transport the inverter by a crane with sufficient load capacity.
The inverter is delivered to the user by the forwarding company. After unloading, the inverter
will be transported to the installation site by the plant staff.
Local standards and regulations on the transport and loading & unloading of the
cabinet, especially those safety instructions, should be observed at all times.
All the accessory appliances to be used during transport should be maintained
beforehand.
The inverter must be transported by qualified personnel. Qualified personnel are those
who have been trained, especially in safety operation.
Keep in mind the dimensions and total weight of the inverter at all times!
Ensure that the following requirements are met:
All the doors are locked.
Choose the appropriate crane or hoist to transport the inverter. The crane or hoist must
be sufficiently capable of bearing the inverter weight.
During transportation, fix the cabinet to the vehicle through the lifting rings at the bottom
and top of the cabinet with ropes, to avoid excessive tilting of the inverter.
When transporting a single inverter, be sure to use ropes to fix the lifting rings at the
bottom four corners and top of the cabinet to the transport vehicle.