EasyManua.ls Logo

Sungrow SG3425UD - Hoisting

Sungrow SG3425UD
110 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
23
A professional instructor is required in the whole hoisting process.
All the used slings must have the load-bearing capacity of at least 10t.
The crane should have sufficient arm length and radius of gyration.
All the connection point must be firmly connected.
The length of the slings can be adjusted appropriately according to on-site conditions.
Transport the inverter in a level, smooth, and steady way.
Transport the inverter by connecting the four top corner fittings.
Some accessories may be required to ensure the safety during hoisting.
The following figure illustrates the hoisting operations. Circle A indicates the work areas of
the crane. Anybody standing inside the circle B is prohibited for safety considerations.
5.2.2 Hoisting
During the whole hoisting process, observe the following rules:
Hoist the inverter in a vertical manner. Do not drag or drop the inverter on any surface.
When the inverter has been hoisted for about 300mm away from the ground, stop to
check if all the connections are still firm. After confirmation, continue hoisting the inverter.
When transported to the final location, the inverter should be put down slowly and
steadily.
The final location should be firm, level, and well-drained. The inverter is supported by
four bottom fittings on the ground.
The inverter should be hoisted by using four top corner fittings as shown in the following
figure.
System Manual 5 Mechanical Installation

Table of Contents

Related product manuals