5. Prepare the output cables:
• DC power cables. Refer to section 12.13.5.
• AC auxiliary power cables (3 phase 480 V). Refer to section 12.13.3.
• AC auxiliary power cables (1 phase 120 V). Refer to section 12.13.4.
• DC auxiliary power cables (24 V). Refer to section 12.13.6.
• Interlock cables. Refer to section 12.13.8.
• Interlock+DC guard cables. Refer to section 12.13.9.
• Optical fiber cables. Refer to section 12.13.11.
• Ethernet cables. Refer to section 12.13.10.
Prepare the cables according to the number of outlets and the requirements of
the devices that are installed at the outlets.
Note: The cables enter the cabinet from the bottom.
6. Make sure that the cable slack is sufficient to guide the cables in the EVSE. Refer
to section 12.8.
7. If you use an Ethernet cable, make sure that the internet connection is available
for an approved service engineer and the network operating center of the
manufacturer.
5.2 Control the space and airflow around the EVSE
1. Make sure that the floor spaces meet the requirements. Refer to section
12.9.
2. Make sure that the air flow inlet and outlet do not become blocked by objects
such as snow, equipment, etc.
5.3 Install the cable ducts
1. Install two flexible cable ducts below the power cabinet.
2. Install traction wires in the cable ducts.
5.4 Prepare the foundation
5.4.1 Prepare a foundation - general procedure
1. Use the correct foundation. Make sure that the foundation is suitable for the
surface on which the cabinet is installed:
Surface
Type of foundation Refer to section
Soil Concrete foundation 5.4.2
Solid floor Metal frame 5.4.3
Solid floor Custom foundation
2. Embed the cables in the ground with or without a cable duct. Refer to the local
rules.
3. Prepare the selected foundation type for the power cabinet.
Pre-installation
36 HVC 200/300/360-EN | 002