Driving modes and rigging for on-road driving
6.6 Rigging the auxiliary hoist
6 - 60 3 302 633 en Operating Instructions GMK5250L
27.09.2017
6.6.5 Lowering/raising the rigging frame
Prerequisite – A minimum of the 7 t base plate lies on the counterweight platform,
– A maximum counterweight combination of 21 t lies on the counterweight
platform.
(A) – Setting down
• Lift the rigging frame (1) onto the counter-
weight combination.
(B) – Lifting
The auxiliary hoist must be removed.
• Sling the rigging frame (1).
• Lift the rigging frame (1) from the counter-
weight combination.
6.6.6 Placing the auxiliary hoist on the counterweight combination
• Lift the auxiliary hoist
–(A) onto the counterweight combination
or
–(B) onto the rigging frame.
The pins (1) must fit into the mountings (2).
• Remove the lifting gear.
• Establish the connections to the turntable:
–
à Establishing/disconnecting the hydraulic
connection
, p. 6 - 61,
–
à Establishing/disconnecting the electrical
connection
, p. 6 - 62,
–
à Creating the connection to the turntable,
p. 6 - 63.

Table of Contents

Other manuals for Manitowoc Grove GMK 5250L

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK 5250L and is the answer not in the manual?

Manitowoc Grove GMK 5250L Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK 5250L
CategoryConstruction Equipment
LanguageEnglish

Related product manuals