Installation and commissioning
4.3 Commissioning the TIM
TIM DNP3
System Manual, 12/2015, C79000-G8976-C253-04
73
Startup activities of the TIM 4R-IE DNP3
Introduction
During startup, the LEDs on the front panel of the TIM 4R-IE DNP3 have a different
significance compared with normal operation. They are optical indicators of the various
startup phases and provide detailed information about any errors detected during startup.
During startup on the TIM 4R-IE DNP3, the "BATF", "P1" and "P2" LEDs have no
significance.
LED displays during startup
The following table summarizes the startup phases.
Table 4- 4 LED activity on the TIM 4R-IE DNP3 during the various startup phases
1 Power ON, followed by hardware
2 Loading the operating system from
flash memory
Off
3 Starting VxWorks operating sys-
Off Off
Loading and starting TIM firmware
5 Initializing flash file system and
starting the start manager
Off Flash-
Off Off Off Off Off
6 Loading and starting P bus driver Off Flash-
Off Off Off Off
7 Loading and starting subscriber
Off Flash-
Off
Off Off Off
8 Loading and starting LAN-COM Off Flash-
Off Off Off
9 Loading and starting subscriber
Off Flash-
Off Off
Off Off
10 Loading and starting time-of-day
Off Flash-
Off
Off Off
11 Loading and starting the TD7 soft-
ware of the TIM (TD7onTIM) on
the TIM
Off Flash-
es
Off
Off Off
12 Loading and starting WAN driver Off Flash-
Off Off
Startup completed or aborted
Startup completed without error
1)
1)
1)
1)
1)
Startup completed with error
2)
2)
2)
2)
2)
13c Startup aborted - user parameter
assignment missing. Module ex-
Off Off
Flashes
Flashes