EasyManuals Logo

ABB TRIO-20.0/27.6-TL-OUTD User Manual

ABB TRIO-20.0/27.6-TL-OUTD
131 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #86 background imageLoading...
Page #86 background image
- 86 -
000033EG
7 - Operation
Commissioning
Do not place objects of any kind on the inverter during operation!
Do not touch the heatsink while the inverter is operating!
Some parts may be very hot and cause burns.
NOTE: Before proceeding with commissioning, make sure you have carried out all the checks
and verications indicated in the section on preliminary checks.
The inverter commissioning procedure is as follows:
• Put the AC+DC disconnect switch in ON position. If there are two sep-
arate external disconnect switches (one for DC and the other for AC),
rst close the AC disconnect switch and then the DC disconnect switch.
There is no order of priority for opening the disconnect switches.
• When the inverter has power, the rst check performed is the one rela-
ting to the input voltage:
- If the DC input voltage is lower than the Vstart voltage (voltage required
to begin the inverter’s grid connection) the b14 icon remains off and the
“Waiting for the sun” message is displayed b10.
- If the DC input voltage is higher than the Vstart voltage the b14 icon is
displayed and the inverter goes to the next stage of the controls.
In both cases the voltage levels and input current are displayed in the
b15 and b16 elds.
The inverter performs a control of grid parameters. The b22 icon, which
represents the grid distribution, can have different statuses:
- Not present, if the mains voltage results as absent.
- ashing, if the mains voltage is present but outside the parameters dic-
tated by the standard of the country of installation.
- Turns on, if the mains voltage is present and within the parameters dic-
tated by the standard of the country of installation. In this condition, the
inverter starts the sequence of grid connection.
This verication can take several minutes (from a minimum of 30 se-
conds up to several minutes), depending on grid conditions and settings
relative to the standard of the country
Vin < Vstart
Vin > Vstart
Vgrid OK
DC
AC
b02 b03 b04 b05 b06 b08 b09b07b01
b11 b12b13 b24 b14 b15 b16 b17 b18
b19
b21
b20
b22
b10 b23

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB TRIO-20.0/27.6-TL-OUTD and is the answer not in the manual?

ABB TRIO-20.0/27.6-TL-OUTD Specifications

General IconGeneral
BrandABB
ModelTRIO-20.0/27.6-TL-OUTD
CategoryInverter
LanguageEnglish

Related product manuals