Manitowoc Published 04-06-18, Control # 231-14 4-59
MLC650 VPC-MAXâ„¢ OPERATOR MANUAL SET-UP AND INSTALLATION
4
Connecting the Mast Top and Second Insert Straps
See Figure 4-53 for the following procedure.
1. Remove the hair pin cotters (1) from the retaining pin (2)
that secures the VPC-MAX
beam links (3).
2. Remove the retaining pin and rotate the beam link
retaining pin brackets (4) from the stored position to the
working position.
3. Install the retaining pin and hair pin cotters to the
retaining pin brackets.
4. Remove the hair pin cotters (5) and retaining pins (6)
that secure the other links and straps.
5. Install the retaining pins and hair pin cotters in the
working position bracket (7).
6. Connect the links to the straps. See "Connecting the
Mast Straps" on page 4-57 and "Connecting the Mast
Straps and Links with Clevis Pins" on page 4-58.
7. Repeat this process for the other side of the mast top
and insert.
STORED POSITION WORKING POSITION
FIGURE 4-53
Item Description
1 Hair Pin Cotter (qty 4)
2 Retaining Pin (qty 2)
3 VPC-MAX Beam Link (qty 4)
4 Beam Link Retaining Pin Bracket (qty 4)
5 Hair Pin Cotter (qty 12)
6 Retaining Pin (qty 6)
7 Working Position Bracket

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc VPC-MAX MLC650 and is the answer not in the manual?

Manitowoc VPC-MAX MLC650 Specifications

General IconGeneral
BrandManitowoc
ModelVPC-MAX MLC650
CategoryConstruction Equipment
LanguageEnglish

Related product manuals