▪ The system includes provision for venlaon
extracon and secondary
containment of oil and water leaks. Remove all the accidental overows or spills
immediately to avoid risk of slips.
▪ Obey all naonal and local rules and safety regulaons when you install the dry
pumping system. Refer the Vacuum Pump and Vacuum System Safety manual
(publicaon number P40040100) before you pump hazardous materials.
▪ Put and secure cables, hoses and pipework during installaon to avoid possible trip
hazard.
▪ Make sure that the installaon area is clean and free from debris and
contaminaon, such as oil, before you put the pump in posion.
For the system to perform to specicaon, give appropriate facilies as given in this
manual.
4.2 Unpack and inspect
WARNING: HEAVY OBJECT
Risk of injury or damag
e to equipment. Use suitable liing equipment to move the
pump. Aach the liing equipment to the liing eye. Do not use loose slings. Take
care when you move the pump into posion, its mass may make it dicult to slide.
The fan cowl is shaped to provide a handhold for posioning the pump. Do not li
the pump using this handhold.
CAUTION: ENVIRONMENTAL SAFETY
Risk of damage t
o environment. Obey all naonal and local legislaon concerning the
impact of the pump on the environment when you install or remove the pump.
The pump is supplied xed by metal brackets to a wooden pallet with a cardboard
surround. These metal brackets should be removed and retained.
To unpack the pump, do the steps that follow:
1. Be careful when you unpack the pump to prevent the excessive shocks. The
excessive shocks can damage the bearings and decrease the life of the pump. The
pump is supplied with sealed inlets and outlets to prevent the entry of dust and
vapour.
2. Do not remove the seals unl the pump is ready t
o be installed on the vacuum
system.
3. Open the cardboard box from the top, remove any excess packaging as required
and remove the pump from the pallet at the xing points using suitable liing
equipment.
4. If the pump is damaged, nofy your supplier and the carrier in wring within three
days. Give the supplier and the carrier the informaon that follows:
▪ Item number of the pump
▪ Order number
▪ Supplier's invoice number
5. Retain all packing materials for inspecon.
6. Do not use the pump if it is damaged.
10/2020 - ©Edwards Limited
Page 26M56635880_D
M56635880_D - Inst
allaon