INSTALLATION
24 OI 248 (EN) REV6 /REV5
6.2 Materials and Equipment to Be Provided by Customer
Materials and equipment not included in the scope of supply are li-
sted in the appendix. They include the following items:
- Tools
- Hoisting equipment
- Testing and measuring equipment
-Materials
- Foundations, anchor bolts and fasteners
- Supports
- Gas for filling the circuit breaker
These materials and equipment must be provided by the station.
6.3 Use of Auxiliary Materials and Supplies
Auxiliary materials and supplies needed for installation are shipped
in the box containing accessories.
Detailed instructions for use of required auxiliary materials and sup-
plies such as lubricants and locking compounds are given in Ap-
pendix A2. The various procedures are indicated in the text of the
instruction manual by abbreviations (such as L1 or S1), which are
explained in the appendix.
6.4 Unpacking the Transport Units
Check the transport units for completeness and lack of damage. In
the event of shipping damage, notify the freight forwarder and your
authorized GE representative immediately.
6.4.1 Base Frame and Operating Mechanisms
• Leave the base frame and operating mechanisms in the packing
unit until installation.
Improper handling of the transport units may result in serious
damage.
Therefore:
- Comply with handling markings and labeling.
- Use hoisting equipment with adequate load-bearing
capacity.
- Do not stand under suspended loads.