3-5-1-2 Turn on the system
Press the Power On/Off switch at the front of the system once.
When the Power On/Off switch on the Control Panel is pressed once, the TMST starts and the software
code is distributed to initiate the scanner.
No status messages are displayed during this process.
3-5-2 Power Off/ Shutdown
NOTE: After turning off a system, wait at least twenty seconds before turning it on again. The system may not
be able to boot if power is recycled too quickly.
3-5-2-1 Back-end Processor Power Down - LOGIQ P3
To power down the system:
1.) Press the Power On/Off switch at the front of the system.
2.) The System-Exit window is displayed.
3.) Using the Trackball or Select key, select Shutdown.
4.) The shutdown process takes a few seconds and is complete when the power status LED is turned
Amber color.
5.) Disconnect the probes.Clean or disinfect all probes as necessary. Store them in their shipping
cases to avoid damage.