4-26 MAC™ 800 2031504-159D
Maintenance
Functional Checkout Procedures
Perform the functional checkout procedures that are applicable to the
procedure that was performed.
Operational Checks
Diagnostic Tests
4. Verify the AC power cord passed inspection.
See “Visual Inspection” on page 3-3 for more information.
5. Verify the battery pack passed inspection.
See “Visual Inspection” on page 3-3 for more information.
6. Verify that all harnesses and internal wiring have been secured.
See “Visual Inspection” on page 3-3 for more information.
7. Verify the fasteners have been replaced and secured.
See “Visual Inspection” on page 3-3 for more information.
1. Verify the power-up self-test passed.
See “Power-Up Self-Test” on page 3-2 for more information.
2. Verify the rhythm strip recorded successfully.
See Chapter 5, “Recording a Resting ECG,” in the MAC™ 800 Operator’s
Manual.
3. Verify the ECG recorded successfully.
See Chapter 5, “Recording a Resting ECG,” in the MAC™ 800 Operator’s
Manual.
4. Verify the ECG was stored successfully.
See Chapter 8, “Managing Internal Storage,” in the MAC™ 800 Operator’s
Manual.
5. Verify that simulated ECG data was transmitted successfully to a receiving
product.
See Chapter 8, “Managing Internal Storage,” in the MAC™ 800 Operator’s
Manual.
6. Verify the display test was successful.
See “Display Test” on page 3-7 for more information.
7. Verify the keyboard test was successful.
See “Keyboard Test” on page 3-9 for more information.
8. Verify the writer test was successful.
See “Writer Test” on page 3-11 for more information.
9. Verify the acquisition module test was successful.
See “Acquisition Module Test” on page 3-10 for more information.
10. Verify the patient lead wire check was successful.
See “Patient Lead Wire Test” on page 3-16 for more information.