Rigging work
12.8 Outrigger operation
12 - 48 3 302 690 en Operating manual
GMK4100L-1
23.11.2017
From the
control units
Starting the engine
• Start the engine from the driver's cab; à p. 4 - 13.
You can also start the engine from the control units;
à p. 12 - 27.
Switching on the lighting
Only the lamp (1) lights up after opening
the door.
• Press any button.
The lights are switched on.
Moving the outrigger beams
H
You can only operate the outrigger beams to the left and right of the control
unit on the operator's side.
• Observe the safety instructions for operating the outriggers;
à p. 12 - 47.
• Press the button
• Additionally press the button for the desired
outrigger beam.
The outrigger beams move until you let go of the respective button or until
the respective end position has been reached.
5 For high-speed mode
6 For normal speed.
1 Extend left
2 Retract left
3 Retract right
4 Extend right
1 + 4 Extend both
2 + 3 Retract both

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK4100L-1 and is the answer not in the manual?

Manitowoc Grove GMK4100L-1 Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK4100L-1
CategoryConstruction Equipment
LanguageEnglish

Related product manuals