Rigging work
12.10 Rigging work on the main boom
12 - 120 3 302 690 en Operating manual
GMK4100L-1
23.11.2017
12.10.7 Installing/removing the lifting limit switch
Function of the lifting limit switch; à p. 11 - 82.
For every reeved hoist rope, you must install a lifting limit switch, attach a
lifting limit switch weight and place it around the hoist rope.
Installing the
lifting limit switch
You can attach the lifting limit switch on the right or left side of main boom
head. Install the switch on the side that is closer to the last rope line leading
upwards. There can also be one lifting limit switch installed on each side.
On the left side
• Plug the lifting limit switch (3) onto the
bracket (2) and secure it with the retaining
pin.
• Lay the cable (4) so that it will not be
damaged during crane operation, and insert
the lifting limit switch into the socket (1).
On the right side
• Plug the lifting limit switch (3) onto the
bracket (2) and secure it with the retaining
pin.
• Lay the cable (4) so that it will not be
damaged during crane operation, and insert
the lifting limit switch into the socket (1).
Connections (5);
à Lattice extension operating
manual
.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Manitowoc Grove GMK4100L-1 and is the answer not in the manual?

Manitowoc Grove GMK4100L-1 Specifications

General IconGeneral
BrandManitowoc
ModelGrove GMK4100L-1
CategoryConstruction Equipment
LanguageEnglish

Related product manuals