Grove Published 01-29-2015, Control # 512-01 8-67
TMS700E SERVICE MANUAL UNDERCARRIAGE
Installation
1. Apply grease (EP-MPG) to the bottom of the outrigger
beam.
2. If removed, install the side adjustable wear pad in the
outrigger beam.
3. Install the bottom wear pads with approximately 3.2 mm
(0.125 in) protruding. This will prevent the beam side
plates from riding on the bottom of the box.
4. Attach a suitable lifting device of straps or belts—instead
of chains to prevent nicking the bottom edges of the
outrigger beam.
5. Slide the beam into the outrigger housing and align the
cylinder bushing with the mounting hole.
6. Apply anti-seeze compound to the clevis pin. Secure the
cylinder barrel to the housing with the clevis pin and
cotter pin.
7. If the OMS string potentiometer was removed, install the
potentiometer at this time. Refer to Outrigger Monitoring
System (Optional—Standard in North America), page 8-
70.
8. Attach the OMS string potentiometer cable (if equipped)
to the attaching point on the outrigger beam.
NOTE: Avoid free-release of cable to prevent damage to
OMS string potentiometer caused by over-range of
cable.
CAUTION
Be sure that the piston side of all outrigger cylinders are
connected to the solenoid valve bank. Reversal of port
connection of the rod and piston sides could result in
severe damage to the cylinders as very high pressure
intensification will occur.
Reference Only