3-73
E Siemens AG 2013 All Rights Reserved
SIMODRIVE POSMO A User Manual (POS1) – 08/2013 Edition
Commissioning
3.1 General commissioning information
The following prerequisites must be fulfilled before commissioning the
drive:
1. Has the drive been completely installed, cabled and is it ready to be
powered–up?
––> Refer to Chapter 2
2. Has the PROFIBUS–DP node address been set at the connection
cover of SIMODRIVE POSMO A?
––> Refer to Chapter 2.3.1
3. Has the terminating resistor been set at the first and last bus
nodes?
––> Refer to Chapter 2.3.1 and Chapter 2.3
4. Is there a master device file (GSD) and has it been installed?
––> Refer to Chapter 4.4.2
SIMODRIVE POSMO A can only be controlled and parameterized via
PROFIBUS. This is the reason that it is absolutely necessary that com-
munications are established between the DP master and the ”DP slave
POSMO A” that is to be commissioned.
What are the communication possibilities?
S C2 master Parameterizing and start–up tool ”SimoCom A”
––> Refer to Chapter 3.2.3
S C1 master SIMATIC S5 or SIMATIC S7
––> Refer to Chapter 4.4
S Third–party master
––> Refer to the documentation associated with the third–party
master
Standalone operation can be set via P100 and P101:11. This means
that operation is possible without PROFIBUS communications (refer to
Chapter 5.5.12).
Prerequisites for
Commissioning
Communications
between master
and slave
3