5.16 Series commissioning
Series commissioning is the process where you transfer the settings of one inverter to a second
inverter.
Procedure
To transfer settings from one inverter to another, proceed as follows:
1. Save your project to your PC or PG.
2. Loading your backed up settings to a second inverter:
Offline commissioning using STARTER (Page 206)
3. If you control your inverter via PROFIsafe, you have to modify the PROFIsafe address.
Configuring the safety functions (Page 112)
4. Perform a reduced acceptance for the safety functions.
Reduced acceptance after a component has been replaced and a firmware change
(Page 366)
You have transferred the settings of the first inverter to a second inverter.