Chapter 2. Installing the SAN Volume Controller 2145-SV1
hardware
There are several steps that you must complete to prepare, and then install the
SAN Volume Controller hardware.
Before you begin
Note: If you are adding a new I/O group to an existing system, there is no need
to turn off the existing, operating system nodes.
Procedure
To install the SAN Volume Controller hardware, complete the following steps.
1. Prepare for the hardware installation by confirming that you have all the
planning information and parts that you require.
2. Install the support rails for the nodes.
3. Install the cable-management arms for the nodes.
4. Install the nodes.
5. Optionally install the expansion enclosures.
6. Connect the Fibre Channel and Ethernet cables to the nodes.
7. Optionally connect the nodes to the expansion enclosures.
8. Verify that the nodes are operational.
Results
After you finish these steps, the hardware installation is complete. The customer is
responsible for all configuration tasks.
Preparing for the SAN Volume Controller 2145-SV1 hardware
installation
You must prepare for the installation of the SAN Volume Controller.
Before you begin
Figure 17 on page 16 shows the major hardware components required.
© Copyright IBM Corp. 2014, 2017 15

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the IBM MTM 2145-SV1 and is the answer not in the manual?

IBM MTM 2145-SV1 Specifications

General IconGeneral
BrandIBM
ModelMTM 2145-SV1
CategoryController
LanguageEnglish

Related product manuals