42
Electrical installation
Connection procedure
1. Fasten the input power cable under the grounding clamp. Crimp a cable lug onto
the grounding conductor (PE) of the cable and fasten the lug under a grounding
clamp screw.
2. Connect the phase conductors to the U1, V1 and W1 terminals. Use a tightening
torque of 0.8 N·m (7 lbf·in).
2
1
3. Strip the motor cable and twist the shield to form as short a pigtail as possible.
Fasten the stripped motor cable under the grounding clamp. Crimp a cable lug
onto the pigtail and fasten the lug under a grounding clamp screw.
3
Tightening torque:
0.8 N·m (7 lbf·in)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB ACS150 series and is the answer not in the manual?

ABB ACS150 series Specifications

General IconGeneral
BrandABB
ModelACS150 series
CategoryController
LanguageEnglish

Related product manuals