INT ER CO NNE CT IO NS ET HER N ET N E T W OR K V ER IF I CAT IO N
16 1VLG 500 0 17 C
Protection relay
Check the connection status of protection relays via PCM600. Open the factory delivered pro-
ject and select the protection relay for which you want to check the connection. If the connec-
tion between the PCM600 and protection relay is established, a green tick mark is shown
next to the protection relay icon.
Figure 24: Example of Plant Structure in PCM600
Network redundancy
Check the availability of voltage measurements and GOOSE signals when the managed Ether-
net switch, communication link or protection relay fails.
GOOSE and Process bus
The GOOSE / SMV alarm is assigned to a configurable LED via the PCM600 and it relates to
function blocks (GSELPRT1 – GOOSE supervision and ULTVTR1 – SMV supervision).

Table of Contents

Other manuals for ABB UniGear Digital

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB UniGear Digital and is the answer not in the manual?

ABB UniGear Digital Specifications

General IconGeneral
BrandABB
ModelUniGear Digital
CategorySwitch
LanguageEnglish

Related product manuals