AP PAR ATUS CO NTR O L T E STI NG PA N E L INT ER N A L I NT ER LO C KING
1VLG5 00 0 17 C 41
Step 6/7
Move the circuit breaker truck into the service position. Close the circuit breaker. Check the
circuit breaker status on the protection relay LHMI.
Figure 59: Single line diagram, the circuit breaker is closed and in the service position
Step 7/7
Check the impossibility of isolating the circuit breaker from service when it is closed.

Table of Contents

Other manuals for ABB UniGear Digital

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB UniGear Digital and is the answer not in the manual?

ABB UniGear Digital Specifications

General IconGeneral
BrandABB
ModelUniGear Digital
CategorySwitch
LanguageEnglish

Related product manuals