INT ER LOCK S BE T W EE N PA NELS AP PAR ATUS CO NTR O L T E STING
50 1VLG5 000 17 C
Step 2/10
Close the circuit breaker in the feeder to be tested. Check the circuit breaker status on the
protection relay LHMI.
Figure 74: Single line diagram circuit, the circuit breaker is closed and in the service position
Step 3/10
Close all upstream breakers in the relative section, such as the Incomer, Generator and Bus
tie.
Step 4/10
On the protection relay LHMI (upstream breaker receiving CBFP trip command) go to -> Main
Menu/Test/IED test
Test mode = IED test
The ready LED is flashing when the protection relay is in the test mode.
Figure 75: Entering test mode
Step 5/10
On the protection relay LHMI (tested feeder) go to -> Main Menu/Test/IED test
Test mode = IED test
The ready LED is flashing when the protection relay is in the test mode.

Table of Contents

Other manuals for ABB UniGear Digital

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB UniGear Digital and is the answer not in the manual?

ABB UniGear Digital Specifications

General IconGeneral
BrandABB
ModelUniGear Digital
CategorySwitch
LanguageEnglish

Related product manuals