FlexiROC T30 R 5 Transport
100 No: 2969809547.1.2969824267 en-US
n The articulation lock must be installed in locked position before loading the machine
onto the transport vehicle.
5.3 Hoisting Drill Rig
WARNING
Suspended Load
Suspended load can cause serious personal injury and property damages.
u Do not approach a suspended load.
u Only use lifting devices and hoisting slings with adequate hoisting capacity.
u Lock the track oscillation cylinders before the drill rig is raised.
1.
Position the boom, feeder, and rock drill so they are in equilibrium.
2.
Support the boom and feeder with straps if necessary.
3.
Place the straps under both crawler tracks at points A and B.
!
NOTE: Make sure there are no hoses, controls, or any other com-
ponents that can fasten or be damaged when the lifting straps be-
come taut.