Figure 13-3 Installing front and rear sealing plates
----End
13.3 Subsequent Operations
Procedure
Step 1 Set all the switches to the appropriate status based on site requirements.
Step 2 Observe the power system for 1 hour and check that no alarm (excluding door
status alarms) is displayed on the liquid crystal display (LCD) of the monitoring
module and that the voltage and current for batteries and loads are normal.
After power-on and commissioning, if the site cannot be powered on, switch o the battery
circuit breaker or disconnect the battery fuse. If the site cannot be powered on within two
months, disconnect the battery loop.
Step 3 Reinstall the removed panel if any.
Step 4 Seal used cable holes with
reproof putty and seal unused cable holes with lids
delivered with the cabinet.
Step 5 Check whether the paint on the surface of the cabinet is intact. Repair any
damaged paint.
Step 6 Lock the cabinet door and hand over the key to the administrator.
PowerCube 1000 (STC, Saudi Arabia, ICC800-A1-C2,
ESC800-A1)
Installation Guide 13 Checking Before Leaving the Site
Issue 02 (2021-09-28) Copyright © Huawei Technologies Co., Ltd. 144