System integration
9.4 ASM 475
MOBY D
260 System Manual, 01/2010, J31069-D0147-A6-7618
9.4.6.3 Lightning protection
Implement lightning protection provided that it is appropriate for your application. An
individual appraisal of the entire plant is necessary before initiating any lightning protection
measures.
9.4.7 Cable
9.4.7.1 Cable assembly by the customer
To achieve electromagnetic compatibility, the SLG cable must be routed via an S7-300
shield connecting element. When the customer assembles the SLG cable, the cable shield
must be exposed (see the figure below).
 
'LPHQVLRQVLQPP
Figure 9-22 Exposure of the cable shield for cable assembly by the customer