7.3
Provision Raman Port Connections
Prerequisites:
■Appropriate Raman ber-opc cable connecon must be completed. For more informaon, refer to Install
L160 Raman Cabling.
â– L100 and L160 Blades must be provisioned
This procedure describes how to provision port-connecon between Raman blade and L100 Blade.
Note: L100 Blade Issue 14, FC95453R11-I14, and later blade must be used with L160 Raman blade.
Step 1
Provision the edge port E1 of L100 Blade.
Note: If autoprovisioning is enabled, the E1 port is automacally provisioned.
Command:
% set eqpt shelf 1 slot 0 cardType BDL1-3R11 subslot 0 port E1 admin-status up
pluggableInterfaceType Edge num-lanes 128
Step 2
Provision the client port C1 on the Raman tributary blade.
Note: If autoprovisioning is enabled, the client port C1 is automacally provisioned.
Command:
% set eqpt shelf 101 slot 0 cardType BDL1-3M21 subslot 0 port C1 admin-status up
pluggableInterfaceType Client num-lanes 128
Step 3
Provision port-connecon between Raman client port and L100 edge port.
Command:
% set port-connection D1-RAMAN src-shelf 101 src-slot 0 src-subslot 0 src-port C1
dst-shelf 1 dst-slot 0 dst-subslot 0 dst-port E1
✓ This task is complete.