10 / 100
Siemens Commissioning Guide CM1G5192en
Building Technologies 3 Mechanical installation 29.07.2010
3.1.2 Clearances for SED2 of the IP20 range
The IP20 range of SED2 units can be mounted side by side without space in between. Keep the following minimal
clearance above and below the VSD for the movement of cooling air:
≥
100 mm
SED2
SIEMENS
SED2
SIEMENS
5192Z41
≥
100 mm
3.1.3 Drilling plan for SED2 IP54
5192M02
H
W
Spacing
Frame
size
H
(mm)
W
(mm)
Mounting material
Tightening
torque
B
342.8 230
4 x M6
screws
4 x M6 nuts
4 x M6
washers
5 Nm
C
564 312.7
4 x M6
screws
4 x M6 nuts
4 x M6
washers
5 Nm
D
647 310
4 x M8
screws
4 x M8 nuts
4 x M8
washers
13 Nm
E
847 310
4 x M8
screws
4 x M8 nuts
4 x M8
washers
13 Nm
F
1112 400
4 x M8
screws
4 x M8 nuts
4 x M8
washers
20 Nm
Frame size Min. vertical clearance V
min.
in mm
A, B, C 100
D, E 300
F 350