Step 22
Did the Main blade had a USB ash drive that was removed in Step 1?
If YES:
Connue with next step.
If NO:
Proceed to Step 26.
Step 23
Insert USB ash drive in the replacement Main blade.
Step 24
Turn the power on at the source and wait for the blade to inialize.
Warning: Aer the blade is powered up, power down within 15 minutes causes database corrupon,
which leads to blade start-up failure and requires a return to factory for reprogramming.
Step 25
Verify that previous OSL and provisioning are restored to Main blade.
Step Result:
Procedure is complete.
Step 26
Is a database backup available for the blade being replaced?
If YES:
Proceed to Restore Conguraon Database and connue with next step.
If NO:
Proceed to Equipment Installaon and connue with next step.
Step 27
Turn the power on at the source and wait for the blade to inialize.
Step 28
Provision the tributary blade equipment.
Command:
> request set-shelfmode shelfid <x> shelfrole TRIB
Step Result:
Procedure is complete.
✓ This task is complete.
System Maintenance
Equipment Replacement
411
Release 19.1.1 · Issue 1.1, May 2021
Fujitsu and Fujitsu Customer Use Only