D
IRECTION 5604324, REVISION 11 DRAFT (JANUARY 24, 2019) SERVICE MANUAL
8-154 Section 8-31 - Replacement of the Cable Hook
Section 8-31
Replacement of the Cable Hook
8-31-1 Manpower
1 Person, 5 minutes.
8-31-2 Tools
Standard Phillips Screwdriver.
8-31-3 Removal Procedure
1) Remove screws as following figure and carefully remove cable hook.
NOTE: Make sure not to lose washers when removing hooks.
Figure 8-182 Removal of Cable hook
8-31-4 Installation Procedure
Parts to be installed in reverse order of removal.
8-31-5 Functional Check
Visual inspection Only.

Table of Contents

Other manuals for GE LOGIQ P9

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE LOGIQ P9 and is the answer not in the manual?

GE LOGIQ P9 Specifications

General IconGeneral
BrandGE
ModelLOGIQ P9
CategoryMedical Equipment
LanguageEnglish

Related product manuals