Chapter 8 - Replacement procedures 8 - 61
2.) Install the two screws for the Rear Handle (torque=3Nm).
3.) Install the four hexcap screws for the Rear Handle.
4.) Install the Top Cover.
5.) Install the Rear Cover.
6.) Install the Side Covers.
WARNINGWARNING
ENERGY CONTROL AND POWER LOCKOUT FOR VIVID E9.
WHEN SERVICING PARTS OF THE SYSTEM WHERE THERE IS EXPOSURE TO
VOLTAGE GREATER THAN 30 VOLTS:
1. FOLLOW LOCK OUT/TAG OUT PROCEDURES.
2. TURN OFF THE BREAKER.
3. UNPLUG THE VIVID E9.
4. MAINTAIN CONTROL OF THE POWER PLUG.
5. WAIT FOR AT LEAST 20 SECONDS FOR CAPACITORS TO DISCHARGE, AS THERE ARE NO TEST POINTS TO
VERIFY ISOLATION. THE AMBER LIGHT ON THE OP PANEL ON/OFF BUTTON WILL TURN OFF.
BEWARE THAT THE MAIN POWER SUPPLY AND BACK END PROCESSOR MAY BE ENERGIZED EVEN IF THE POWER
IS TURNED OFF WHEN THE CORD IS STILL PLUGGED INTO THE AC OUTLET.
Signed
Date
TA G
&
LOCKOUT