Series 8 C300 Controller User's Guide
Honeywell
7. C300 Controller Operation
7.10. Initiating Switchover command
7.10
Initiating Switchover command
Perform the following procedure to initiate a switchover command manually to a
redundant C300 Controller pair.
Prerequisites
ï‚·
You can view active redundant C300 Controller pair on the Monitoring tab in
Control Builder.
ï‚·
The primary and secondary C300 Controllers are synchronized.
Commanding a switchover
To initiate a switchover, perform the following steps.
In the Monitoring tab, double-click the primary C300 icon. The Parameters
configuration form appears.
Click the Redundancy tab to display it.
Click Initiate Switchover.
Click Yes to confirm the action and issue the switchover command.
Confirm that the Secondary C300 Controller assumes the Primary role. The
old primary controller should boot up in the backup role.
Click OK to close the Parameters form.
This completes the procedure.