7.2.1 Installation Overview
Installation Process
Figure 7-2 Installation process
Precautions
● Properly ground the server before installation to avoid damage to electronic
components from electrostatic discharge. Improper grounding may cause
electrostatic discharge.
For details about how to prevent electrostatic discharge, see 6.1 ESD
Prevention.
● Before installing multiple components, read the installation instructions for all
the components and identify similar actions to simply the installation process.
Use the Intelligent Computing Compatibility Checker to obtain information
about the components supported.
Wait until overheating devices have cooled down before touching them to avoid
injury.
7.2.2 Unpacking the Server
Procedure
Step 1 Check whether the packing case and seals are in good conditions.
FusionServer Pro 2288X V5 Server
User Guide 7 Installation and Conguration
Issue 04 (2020-06-05) Copyright © Huawei Technologies Co., Ltd. 71