7.2.5.2 Installing the Server on the Ball Bearing Rail Kit
Before installing the server, ensure that the ball bearing rail kit is properly
installed. For details, see 7.2.4.3 Installing the Ball Bearing Rail Kit.
Procedure
Step 1 Install the server.
NO TICE
At least two people are required to move the device. Otherwise, personal injury or
device damage may occur.
1. Pull out the inner rails as far as they will go.
Figure 7-9 Pulling out an inner rail
2. Lift the server (at least two people are required), align the two mounting
screws on the rear part of the server with the holes on the inner rails, and
push the server horizontally until the server cannot move. See Figure 7-10.
FusionServer Pro 2288X V5 Server
User Guide 7 Installation and Conguration
Issue 04 (2020-06-05) Copyright © Huawei Technologies Co., Ltd. 79

Table of Contents

Other manuals for Huawei FusionServer Pro 2288X V5

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionServer Pro 2288X V5 and is the answer not in the manual?

Huawei FusionServer Pro 2288X V5 Specifications

General IconGeneral
BrandHuawei
ModelFusionServer Pro 2288X V5
CategoryServer
LanguageEnglish

Related product manuals