If the packing case is soaked or deformed, or the seals or pressure-sensitive adhesive tapes
are not intact,
ll in the Cargo Problem Feedback Form.
Step 2 Use a box cutter to open the packing case.
Exercise caution with the box cutter to avoid injury to your hands or damage to
devices.
Step 3 Unpack the packing case.
Step 4 Ensure that the components are complete and in good condition without defects
such as oxidation, chemical corrosion, missing components, or other damage
incurred during transport.
Table 7-2 Packing list
No. Description
1 (Optional) Documentation bag containing a warranty card and
quick start guide
2 Server guide rails
3 One rack server
----End
7.2.3 Installing Optional Parts
Before installing and conguring a server, you need to install all optional parts
required, such as extra CPUs, drives, and PCIe cards.
Procedure
Step 1 Install the optional parts for the 2288X V5.
For details, see FusionServer Pro 2288X V5 Server V100R005 Maintenance and
Service Guide.
----End
7.2.4 Installing Server Guide Rails
7.2.4.1 Installing L-Shaped Guide Rails
L-shaped guide rails are designed for Huawei cabinets only.
The 2288X V5 servers are stackable onto L-shaped guide rails.
FusionServer Pro 2288X V5 Server
User Guide 7 Installation and Conguration
Issue 04 (2020-06-05) Copyright © Huawei Technologies Co., Ltd. 72