OPERATION OF THE MACHINE72
BDigging and Loading
C Loading a sand pile
1. Direct the bucket blade parallel to the ground and
advance the machine to drive the bucket into the sand
pile.
2. When the bucket is sufficiently driven into the sand, lift
the bucket while advancing the machine.
3. If the bucket is insufficiently driven into the sand, move
the bucket blade up and down while moving forward.
C Digging and loading from flat ground
1. Direct the bucket blade slightly downward and lower
the bucket as you advance the machine.
The recommended digging depth per pass is between
10 and 15cm (4-6").
2. While adjusting the vertical movement of the bucket,
lift the bucket so that sand can be removed by layers.
Continue in this manner as you advance the machine.