18 PIST0017 - System Cable Routing
18.1 Personnel Requirements
Personnel
Requirements
Preliminary Reqs Procedure Finalization
1 0 min 9 hours Not Applicable
18.2 Overview
The cables sets are delivered on a pallet, lengths were defined during ordering process, with the
cable select process. The pallet includes group 1 under group 2 on two independent spools,
the group 3 is delivered in a separate box. The pallet could be used as a tool, to unspool the
cables sets. This tool includes the axis , the two wooden forms and the support .
Illustration 6-27:
18.3 Preliminary Requirements
18.3.1 Tools and Test Equipment
Item
Qty Effectivity Part# Manufacturer
Standard engineer’s toolkit. 1 - - -
18.3.2 Safety
Follow the procedure to unpack the spool.
Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare Direction 5160944-13-1EN, Revision 2
214 18 PIST0017 - System Cable Routing