5 Pre-Installation Checklist
GE Healthcare Site Readiness Checklist
GEHC Global Order # :
Customer:
GEHC On-site Representative :
MI Supplier:
Name of customer reviewed with :
Lead Installer:
GEHC PMI :
Phone Number:
Target Site Prep Completion Date:
Helper:
The customer is responsible for proper site preparation and site readiness regardless of any GEHC inspections/assessments.
For MR Magnet Delivery: Ensure cryogen vents, power for the cooling system and exhaust fan system are installed and operational (0.7T, 1.5T
& 3T) and chilled water supply is available 24x7 that meets system cooling equipment requirements.
Inspection Date:
Item #
GEHC Minimum Requirements
Storage: Is
item
ready?
Predict (Pre-ship)
Verify (Deliv‐
ery):
Is item ready?
Validate
(Mech In‐
stall):
Is item
ready?
Comments
If "N", please enter in comments
or action plan
Is this
item
ready?
Will item
be
ready?
1
Equipment installation drawings must
match actual room size and must meet
clearance requirements. Deviations that
meet installation requirements may be red-
lined, if red-lining is allowed by local code.
Seismic requirements are identified on
construction drawings.
X
2
Delivery route to installation or storage
area meets requirements and has been
discussed and scheduled with the custom‐
er. Ensure floor protection is discussed,
requirements identified, and will be availa‐
ble at time of delivery and installation.
X
3
Rooms that will contain equipment, includ‐
ing storage areas, are dust free. Room
security to prevent unauthorized access
and theft has been discussed with custom‐
er. The customer is aware of these security
issues, implications and responsibility.
4
In room HVAC ductwork and units (in
room) must be mechanically installed and
dust free. Installation rooms appear to
meet environmental conditions (see Fur‐
ther Definitions) and observed issues have
been communicated to the customer. If be‐
ing stored, storage area must meet PIM
storage criteria.
5
Ceiling grid is installed, Unistrut is located
per the installation drawings, and perma‐
nent lighting is installed and operational.
X
6
Floor is clean and prepared for final floor
covering. Customer has verified floor lev‐
eling meets the equipment installation
drawings and PIM specs and no visible de‐
fects are observed. Gantry and table base‐
plate are installed prior to delivery (if
applicable)
X
7
Access to a working phone at the facility for
emergency use, including MR magnet de‐
livery.
X