Hose/Applicator Expansion Base
G-4
Part 1128350_02
E 2020 Nordson Corporation
Power Requirements
If the melter's electrical service wiring is already sized to support
6 hoses/applicators, then no changes are required when installing t he
hose/applicator expansion base. For information about sizing t he melter
electrical service, refer to Configure the Electrical Service given earlier
manual in Installation (Section 1).
RemovingtheMelterfromtheSub-Base
To install the expansion base on the melter, you must first remove the
sub-base from the melter.
1. Disconnect supply power to the melter.
2. Disconnect melter hoses and air supply line.
3. (Optional) If the input power cable was routed into the melter through the
knockoutinthesub-base,disconnectthepowercablefromTB1onthe
main board, and then remove the cable from the sub-base.
4. SeeFigureG-3.Usea6mmhexwrenchtoremovethetwoM8
socket-head cap screws on the front of the chassis. Retain the screws.
Figure G-3 Remove melter from the sub-base