CHAPTER 4
Chassis Installation
This chapter describes how to install the ASR 5500 chassis and its components.
The ASR 5500 is suitable for installation in Network Telecommunication Facilities designed for unattended
equipment operation.
Important
This chapter includes the following sections:
•
Mounting Options, page 31
•
Weight Considerations, page 32
•
Unpacking the Chassis, page 32
•
Reducing the Weight of the Chassis Prior to Installation, page 35
•
Installing the Chassis, page 40
•
Grounding the Chassis, page 43
•
Re-Installing Chassis Components, page 45
•
Cable Management System, page 47
Mounting Options
There are two options for mounting the chassis in a standard 19-inch equipment rack or telecommunications
cabinet:
•
Flush mount: In this configuration, the flanges of the mounting brackets are flush with the front of the
chassis. This is the default configuration as shipped. This method is typically used to mount the chassis
in a 4-post rack or equipment cabinet. Refer to
•
Mid-mount: In this configuration, the flanges of the mounting brackets are recessed from the front of
the chassis. To do this, the mounting brackets must be removed and reinstalled toward the middle of the
chassis. This method is typically used to mount the chassis in a two-post rack. Refer to
ASR 5500 Installation Guide
31

Table of Contents

Other manuals for Cisco ASR 5500

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Cisco ASR 5500 and is the answer not in the manual?

Cisco ASR 5500 Specifications

General IconGeneral
BrandCisco
ModelASR 5500
CategoryNetwork Router
LanguageEnglish

Related product manuals