Figure 10-12 Installing the mounting ears reversely
Step 2 Slide a BBU along the guide rails into an OMB, and then tighten four M6x16 screws on the
panel until the tightening torque reaches 3 N·m, as shown in Figure 10-13.
Figure 10-13 Installing a BBU
----End
10.4 Installing Cables
This section describes the procedures and precautions to be taken for installing power cables,
transmission cables, monitoring signal cables, and CPRI cables when a DBS3900 is deployed
outdoors and the BBU is installed in an OMB.