0B-13 Maintenance and Lubrication:
Throttle Cable Play Inspection and Adjustment
B827H10206013
Inspect throttle cable play
Initially at 200 km (100 miles, 1 month) and every 1
000 km (600 miles, 3 months) thereafter
Inspect and adjust the throttle cable play “a” as follows.
Throttle cable play “a”
3.0 – 5.0 mm (0.12 – 0.20 in)
1) Remove the boot (1).
2) Loosen the lock-nut (2) of the throttle cable.
3) Turn the adjuster (3) in or out so that the throttle
cable play “a” at the throttle lever end is between 3 –
5 mm (0.12 – 0.20 in).
4) Tighten the lock-nut (2) while holding the adjuster
(3).
5) Reinstall the boot (1) firmly.
WARNING
!
After the adjustment is completed, check that
handlebar movement does not raise the
engine idle speed and that the throttle lever
returns smoothly and automatically.
Engine Idle Speed Adjustment
B827H10206030
Inspect initially
Initially at 200 km (100 miles, 1 months) and every 1
000 km (600 miles, 3 months) thereafter.
Adjust the idle speed in the following procedures:
NOTE
Make this adjustment when the engine is hot.
1) Remove the left side cover. Refer to “Exterior Parts
Removal and Installation in Section 9D (Page 9D-
3)”.
2) Connect the electric tachometer or multi-circuit tester
to the high-tension cord.
3) Start the engine and set the engine idle speed
between 1 400 and 1 600 r/min by turning the throttle
stop screw knob (1).
Engine idle speed
1 500 ± 100 r/min
Special tool
: 09900–26006 (Engine tachometer (solar
cell type))
: 09900–25008 (Multi-circuit tester set)
Drive V-belt Inspection (LT-A400/F)
B827H10206016
Inspect drive V-belt
Every 1 000 km (600 miles, 3 months)
Inspect the drive V-belt in the following procedures:
1) Remove the drive V-belt. Refer to “V-belt Type
Continuously Variable Automatic Transmission
Removal and Installation in Section 5A (Page 5A-7)”.
2) Inspect the drive V-belt for crack or other damage
and measure the width of belt if necessary. If any
abnormal point are found, replace the drive V-belt
with a new one. Refer to “V-belt Type Continuously
Variable Automatic Transmission Removal and
Installation in Section 5A (Page 5A-7)”.
3) Install the removed parts. Refer to “V-belt Type
Continuously Variable Automatic Transmission
Removal and Installation in Section 5A (Page 5A-7)”.
2
3
1
“a”
I827H1020038-02
1
I827H1020024-01
I827H1020051-01

Table of Contents

Other manuals for Suzuki LT-F400F

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Suzuki LT-F400F and is the answer not in the manual?

Suzuki LT-F400F Specifications

General IconGeneral
BrandSuzuki
ModelLT-F400F
CategoryOffroad Vehicle
LanguageEnglish

Related product manuals