In case a manually operated activation switch is used, the switch must be of a type
that can be locked out to the open position.
The contacts of the switch or relay must open/close within 200 ms of each other.
Cable types and lengths
Double-shielded twisted-pair cable is recommended.
Maximum cable lengths:
300 m (1000 ft) between activation switch [K] and drive control unit
60 m (200 ft) between multiple drives
60 m (200 ft) between external power supply and first control unit
Note: A short-circuit in the wiring between the switch and an STO terminal causes a
dangerous fault. Therefore, it is recommended to use a safety relay (including wiring
diagnostics) or a wiring method (shield grounding, channel separation) which reduces
or eliminates the risk caused by the short-circuit.
Note: The voltage at the STO input terminals of the drive must be at least 13 V DC to
be interpreted as “1”.
The pulse tolerance of the input channels is 1 ms.
Grounding of protective shields
Ground the shield in the cabling between the activation switch and the control unit
at the control unit only.
Ground the shield in the cabling between two control units at one control unit only.
The Safe torque off function 191

Table of Contents

Other manuals for ABB ACS380

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB ACS380 and is the answer not in the manual?

ABB ACS380 Specifications

General IconGeneral
BrandABB
ModelACS380
CategoryDC Drives
LanguageEnglish

Related product manuals